Infrastructure & bridges
Bridges and roads that open the site
River bridges, industrial-park roads, container yards and utilities — the civil works that decide whether a plant can open on time.
Request a quoteOur infrastructure division began in 2013 with the Hòa Xuân approach spans in Đà Nẵng. Today it builds balanced-cantilever and precast bridges, park road networks, heavy-duty container yards and the drainage and utilities beneath them — for provincial transport boards, park developers and port operators. Sixty-two bridges and road packages, every one handed over without a lost-time injury since 2020.
Scope of work
01Bridges
Balanced-cantilever, precast I-girder and steel composite, spans to 180 m
02Roads
Industrial-park and access roads, asphalt and rigid pavement
03Ports & yards
Heavy-duty container pavement, crane rails and marshalling areas
04Drainage
Box culverts, storm drains and retention ponds
05Utilities
Water, wastewater and power corridors for industrial parks
06Ground works
Soft-soil improvement, PVD and surcharge, bored piling
How a bridge comes together
01Survey & design
8–16 weeksTopography, geotechnics, hydrology and design
02Approvals
4–10 weeksTransport-board and waterway permits
03Foundations
12–20 weeksBored piles, cofferdams and pile caps
04Substructure
10–16 weeksPiers, abutments and bearings
05Superstructure
16–30 weeksCantilever segments or girder launch, deck
06Finishing & handover
4–8 weeksSurfacing, joints, load test
Plant & equipment on a typical site
| Equipment | Specification | Units |
|---|---|---|
| Form travellers | Balanced-cantilever, 4.5 m segments | 4 pairs |
| Launching gantry | 40 m girders, 180 t | 1 |
| Bored piling rigs | D1500 to 70 m | 4 |
| Crawler crane | 250 t, barge-mounted | 1 |
| Asphalt paver | 9 m screed | 2 |
| Survey | GNSS, robotic total station, deflection monitoring | 3 teams |