Industrial plants
Industrial plants, built to run on day one
Electronics, food and precision-engineering plants delivered EPC — one contract from soil survey to commissioning, one team accountable for the handover date.
Request a quoteA production plant is judged on the day the first line starts, not the day the roof goes on. We plan backwards from that day: process layout and utility loads first, structure around them, and a commissioning sequence agreed with your engineers before we break ground. Since 2004 we have delivered 164 plants for electronics, automotive-parts, food and pharmaceutical manufacturers in fourteen industrial parks.
Scope of work
01Feasibility & permits
Site survey, EIA support, fire-safety and construction permits with the park authority
02Design & engineering
Process-led layouts, structural and MEP design in one BIM model to LOD 400
03Procurement
Steel from our own shop, long-lead MEP equipment tendered and expedited by our team
04Construction
Piling, slab, steel erection, envelope and fit-out under one site management
05MEP & clean rooms
Power to 22 kV, HVAC, compressed air, clean rooms to ISO 7
06Commissioning
Integrated systems testing, as-built documents and a 24-month defects period
How a plant comes together
01Concept & budget
4–6 weeksLayout options, capex estimate within ±10%
02Detailed design
8–12 weeksPermit and construction drawings, BIM coordination
03Foundations & slab
10–14 weeksPiling, ground beams, FM2 floor slab
04Structure & envelope
12–16 weeksSteel erection, roof and cladding, weather-tight
05MEP & fit-out
14–20 weeksUtilities, clean rooms, offices, external works
06Test & handover
4–6 weeksCommissioning, training, as-built record
Plant & equipment on a typical site
| Equipment | Specification | Units |
|---|---|---|
| Crawler crane | 150 t, 60 m boom | 2 |
| Tower crane | 8 t at 55 m jib | 1–2 |
| Hydraulic piling rig | D600 bored piles to 45 m | 3 |
| Laser screed | Somero-class, FM2 flatness | 1 |
| Mobile elevating platforms | 16–26 m working height | 12 |
| Survey | Robotic total station, GNSS rover | 2 teams |