Warehouses & logistics
Warehouses built for throughput
Ambient and cold-chain distribution centres, cross-docks and high-bay stores — floors flat enough for very-narrow-aisle trucks, docks sized to the fleet, handed over on the date the lease starts.
Request a quoteA warehouse earns its money in pallet moves per hour. We start from your racking layout, truck fleet and cold-chain temperatures, then design the slab, column grid and dock apron around them. Since 2008 we have built 128 logistics facilities — from a 6,000 m² cross-dock in Bình Dương to the 120,000 m² regional hub in Long An — most of them on fast-track programmes tied to a lease date.
Scope of work
01Site & layout
Racking, dock and yard layouts developed with your operations team
02Superflat floors
FM2 and DM-class slabs for VNA and high-bay racking, laser-screeded
03Portal frames
Clear spans to 48 m, eaves to 32 m, from our own steel shop
04Docks & yards
Levellers, shelters, heavy-duty pavement and truck marshalling
05Cold chain
Insulated panels, blast freezers and refrigeration to −25 °C
06Fire & MEP
ESFR sprinklers, LED lighting, rooftop solar and BMS
How a warehouse comes together
01Brief & layout
2–4 weeksThroughput model, racking and dock plan
02Design & permits
6–10 weeksStructural, civil and fire design, park approvals
03Civil & slab
8–12 weeksGround improvement, piling, superflat slab
04Steel & envelope
8–12 weeksFrames, roof, cladding and insulated panels
05MEP & docks
8–12 weeksSprinklers, refrigeration, docks and yards
06Handover
2–4 weeksTesting, fire acceptance, as-built record
Plant & equipment on a typical site
| Equipment | Specification | Units |
|---|---|---|
| Laser screed | Somero-class, FM2 flatness | 2 |
| Power trowels | Ride-on, twin rotor | 8 |
| Crawler crane | 100 t, 50 m boom | 2 |
| Mobile cranes | 50 t all-terrain | 3 |
| Floor profilograph | Continuous F-number survey | 1 |
| Mobile elevating platforms | 16–34 m working height | 18 |