Kanto Precision electronics plant
Kanto Precision Vietnam Co., Ltd.
- Yên Phong II Industrial Park, Bắc Ninh
- 48,000 m²
- 2025
- EPC lump sum
Project overview
A two-storey production building for surface-mount electronics, with an ISO 7 clean room over a third of the floor, a 22 kV substation, a wastewater plant and a four-storey office block. The client needed its first line running fourteen months after we broke ground — before the end of its tax-incentive window.
01The challenge
Fourteen months, fixed. The site was a rice paddy with soft clay to eighteen metres, the rainy season would take four of those months, and the clean-room equipment was due from Japan in month ten whether the building was ready or not.
02Our solution
We drove precast piles through the dry season on a double shift, pre-fabricated all 2,400 tonnes of steel in our Hải Phòng shop while the piles went in, and closed the roof before the first monsoon week. The clean room was built as a sealed box inside the weather-tight shell, so equipment could land in month ten as promised.
Project data sheetDS-2025-014
| Client | Kanto Precision Vietnam Co., Ltd. |
|---|---|
| Location | Yên Phong II Industrial Park, Bắc Ninh |
| Site area | 9.6 ha |
| Gross floor area | 48,000 m² |
| Contract | EPC lump sum, FIDIC Silver Book |
| Structure | Steel portal frames, 36 m clear span |
| Clean room | ISO 7, 16,000 m² |
| Floor | FM2 superflat, 5 t/m² live load |
| Duration | 14 months |
| Handover | March 2025 |
- Months, ground-break to first line
- 14
- Steel fabricated in our own shop
- 2,400 t
- Safe man-hours, zero lost-time injuries
- 1.2M
Fig. 01 — SMT production hall, month 13 Fig. 02 — Roof steel, month 6 Fig. 03 — Truss fabrication, Hải Phòng shop
“Stonebridge gave us a date on the first day and never moved it. Our first board came off the line on the fourteenth month.”